Daftar Proyek Percepatan
Pembangunan Pembangkit Tahap 2
Provinsi
|
Pemilik
|
Jenis
|
Proyek Pembangkit
|
MW
|
COD
|
Aceh
|
Swasta
|
PLTP
|
Jaboi
|
2 x 5
|
2019
|
PLTA
|
Peusangan-4
|
83
|
2020
|
||
PLTP
|
Seulawah
Agam
|
110
|
2024
|
||
Banten
|
Swasta
|
PLTP
|
Rawa Dano
|
110
|
2019
|
PLTP
|
Gunung
Endut
|
40
|
2021
|
||
Bengkulu
|
PLN
|
PLTP
|
Hululais
|
2 x 55
|
2018-2019
|
Jambi
|
PLN
|
PLTP
|
Sungai
Penuh
|
2 x 55
|
2024
|
Jawa Barat
|
PLN
|
PLTA
|
Upper
Cisokan PS
|
4 x 260
|
2019
|
PLTA
|
Jatigede
|
2 x 55
|
2019
|
||
PLTU
|
Indramayu
|
1,000
|
2019
|
||
PLTU
|
Jawa-6
|
2 x 1,000
|
2023
|
||
Swasta
|
PLTP
|
Patuha
|
2 x 55
|
2014 &
2019
|
|
PLTP
|
Kamojang 5
|
30
|
2015
|
||
PLTP
|
Karaha
Bodas
|
30
|
2016
|
||
PLTP
|
Tangkuban
Perahu 1
|
2 x 55
|
2019-2020
|
||
PLTP
|
Cibuni
|
10
|
2020
|
||
PLTP
|
Cisolok-Cisukarame
|
50
|
2020
|
||
PLTP
|
Karaha
Bodas
|
2 x 55
|
2020
|
||
PLTP
|
Tampomas
|
45
|
2020
|
||
PLTP
|
Tangkuban
Perahu 2
|
2 x 30
|
2020
|
||
PLTP
|
Wayang
Windu 3-4
|
2 x 110
|
2020
|
||
PLTP
|
Gunung
Ciremai
|
2 x 55
|
2022
|
||
PLTU
|
Jawa-1
|
1,000
|
2019
|
||
PLTU
|
Jawa-3
|
2 x 660
|
2021-2022
|
||
PLTU
|
Jawa-5
|
2 x 1,000
|
2021-2022
|
||
Jawa
Tengah
|
Swasta
|
PLTP
|
Dieng
|
55
|
2019
|
PLTP
|
Baturaden
|
2 x 110
|
2021
|
||
PLTP
|
Dieng
|
60
|
2021
|
||
PLTP
|
Guci
|
55
|
2021
|
||
PLTP
|
Ungaran
|
55
|
2021
|
||
PLTP
|
Umbul
Telumoyo
|
55
|
2022
|
||
PLTU
|
Jawa-4
|
2 x 1,000
|
2019-2020
|
||
Jawa Timur
|
Swasta
|
PLTP
|
Ijen
|
2 x 55
|
2020
|
PLTP
|
Wilis/Ngebel
|
3 x 55
|
2020-2021
|
||
PLTP
|
Iyang
Argopuro
|
55
|
2021
|
||
Kalbar
|
PLN
|
PLTU
|
Parit Baru
|
2 x 50
|
2017-2018
|
Kalsel
|
Swasta
|
PLTU
|
Kalsel
|
2 x 100
|
2018-2019
|
Kalteng
|
PLN
|
PLTG
|
Bangkanai
|
280
|
2016-2017
|
Kaltim
|
Swasta
|
PLTU
|
Kaltim
|
2 x 100
|
2018-2019
|
Lampung
|
Swasta
|
PLTA
|
Semangka
|
2 x 28
|
2018
|
PLTP
|
Ulubelu 3
dan 4
|
2 x 55
|
2016-2017
|
||
PLTP
|
Suoh
Sekincau
|
4 x 55
|
2020-2024
|
||
PLTP
|
Danau
Ranau
|
2 x 55
|
2022
|
||
PLTP
|
Wai Ratai
|
55
|
2022
|
||
PLTP
|
Rajabasa
|
2 x 110
|
2023-2024
|
||
Maluku
|
PLN
|
PLTP
|
Tulehu
|
2 x 10
|
2018-2019
|
Maluku
Utara
|
Swasta
|
PLTP
|
Songa
Wayaua
|
5
|
2020
|
PLTP
|
Jailolo
|
4 x 10
|
2021-2023
|
||
NTB
|
PLN
|
PLTP
|
Sembalun
|
2 x 10
|
2021
|
PLTU
|
Lombok
|
2 x 50
|
2018-2019
|
||
Swasta
|
PLTP
|
Hu'u
|
2 x 10
|
2024
|
|
NTT
|
Swasta
|
PLTP
|
Atadei
|
2 x 2.5
|
2019
|
PLTP
|
Mataloko
|
20
|
2019
|
||
PLTP
|
Sokoria
|
30
|
2020-2023
|
||
PLTP
|
Oka Ile
Ange
|
10
|
2021
|
Kaltim
|
Swasta
|
PLTU
|
Kaltim
|
2 x 100
|
2018-2019
|
Lampung
|
Swasta
|
PLTA
|
Semangka
|
2 x 28
|
2018
|
PLTP
|
Ulubelu 3
dan 4
|
2 x 55
|
2016-2017
|
||
PLTP
|
Suoh
Sekincau
|
4 x 55
|
2020-2024
|
||
PLTP
|
Danau
Ranau
|
2 x 55
|
2022
|
||
PLTP
|
Wai Ratai
|
55
|
2022
|
||
PLTP
|
Rajabasa
|
2 x 110
|
2023-2024
|
||
Maluku
|
PLN
|
PLTP
|
Tulehu
|
2 x 10
|
2018-2019
|
Maluku
Utara
|
Swasta
|
PLTP
|
Songa
Wayaua
|
5
|
2020
|
PLTP
|
Jailolo
|
4 x 10
|
2021-2023
|
||
NTB
|
PLN
|
PLTP
|
Sembalun
|
2 x 10
|
2021
|
PLTU
|
Lombok
|
2 x 50
|
2018-2019
|
||
Swasta
|
PLTP
|
Hu'u
|
2 x 10
|
2024
|
|
NTT
|
Swasta
|
PLTP
|
Atadei
|
2 x 2.5
|
2019
|
PLTP
|
Mataloko
|
20
|
2019
|
||
PLTP
|
Sokoria
|
30
|
2020-2023
|
||
PLTP
|
Oka Ile
Ange
|
10
|
2021
|
Provinsi
|
Pemilik
|
Jenis
|
Proyek Pembangkit
|
MW
|
COD
|
Sulsel
|
PLN
|
PLTU
|
Punagaya
|
2 x 100
|
2017-2018
|
Swasta
|
PLTA
|
Malea
|
2 x 45
|
2020
|
|
PLTA
|
Bonto Batu
|
110
|
2024
|
||
Sulteng
|
Swasta
|
PLTP
|
Bora Pulu
|
40
|
2022
|
PLTP
|
Marana
|
2 x 10
|
2022
|
||
Sulut
|
PLN
|
PLTP
|
Kotamobagu
|
80
|
2024
|
Swasta
|
PLTP
|
Lahendong V dan VI
|
2 x 20
|
2017-2018
|
|
Sumbar
|
PLN
|
PLTA
|
Masang 2
|
55
|
2020
|
Swasta
|
PLTP
|
Muaralaboh
|
2 x 110
|
2017-2018
|
|
PLTP
|
Bonjol
|
60
|
2022
|
||
Sumsel
|
Swasta
|
PLTP
|
Lumut Balai
|
4 x 55
|
2017-2019
|
PLTP
|
Rantau Dadap
|
2 x 110
|
2019-2020
|
||
Sumut
|
PLN
|
PLTA
|
Asahan 3
|
2 x 87
|
2018
|
PLTU
|
Pangkalan Susu 3 dan 4
|
2 x 200
|
2016-2017
|
||
Swasta
|
PLTA
|
Wampu
|
3 x 15
|
2015
|
|
PLTA
|
Hasang
|
40
|
2018
|
||
PLTP
|
Sarulla 1
|
3 x 110
|
2017-2018
|
||
PLTP
|
Sorik Marapi
|
240
|
2020-2021
|
||
PLTP
|
Sarulla 2
|
2 x 55
|
2022
|
||
PLTP
|
Simbolon Samosir
|
2 x 55
|
2022
|
||
PLTP
|
Sipoholon Ria-ria
|
20
|
2022
|
||
JUMLAH
|
17,458
|
||||
Terdapat 1 proyek yang dikeluarkan dari FTP2 melalui Peraturan Menteri ESDM No. 32 Tahun 2014, yaitu PLTU Madura yang telah diterminasi karena pengembang tidak berhasil membentuk SPC dan tidak mampu mencapai financial closing. Selain itu juga terdapat perubahan kapasitas beberapa PLTP sesuai hasil lelang WKP dan potensi panas bumi.
Porsi pembangkit EBT (PLTP dan PLTA) dalam FTP2 akan menjadi 38%. Pengembangan ini merupakan bagian dari rencana yang lebih besar lagi dalam RUPTL yang mencapai 14.000 MW hingga tahun 2024. Program Percepatan Pembangunan Pembangkit Tahap 2 sebesar 17.458 MW tersebut terdiri atas 5.799 MW sebagai proyek PLN dan 11.659 MW sebagai proyek IPP.
Sumber : RUPTL PLN 2015-2024